2026 Changes Part 2 – WA Quiz Please sign up for the before taking this quiz. Back Save Progress Retry Finish 1. 34 – 2026 code change part 21Who must conduct the performance testing of the GFPE system serving marinas and piers? A qualified person acceptable to the authority having jurisdiction The installing electrician only A manufacturer’s representative Any licensed electrical contractor 555.35 F 2. 78 – 2026 code change part 21Which of the following three‑phase circuits does NOT require Class A GFCI protection 277/480 V 120/208 V 680.5 B 3. 58 – 2026 code change part 21Which installation condition allows the supply circuit rating for EV charging equipment to be less than the full load? When load‑management controls restrict the total load When the EVSE is cord‑and‑plug connected When the EVSE is installed in a dwelling unit When the EVSE is rated 40 amperes or less 625.42 4. 141 – 2026 code change part 21Which of the following is an example of a device that combines control signals with Class 4 emergency power? A Class 4 FMPS transmitter capable of supplying power and control on the same conductors A Class 2 power supply A standard 0–10V dimmer A battery‑equipped emergency luminaire 700.28 A B Informational note 5. 119 – 2026 code change part 21Fuel cell system DC circuits installed in one‑ and two‑family dwellings must comply with a maximum voltage limit of __________ volts.(By setting clear voltage limits the National Electric Code aims to enhance the safety and reliability of fuel cell systems) 600 300 750 1000 692.7 6. 197 – 2026 code change part 21Metal raceways containing entrance wire or cable for limited‑energy systems must be connected to a grounding electrode using ____ A bonding conductor or grounding electrode conductor Only a metallic conduit body A listed surge arrester A grounding bushing only 750.42 7. 182 – 2026 code change part 21Part ______ In article 722 covers limited energy cables and wiring methods. 3 5 7 9 722.12 8. 43 – 2026 code change part 21Which of the following is not permitted to share the elevator car lighting branch circuit? Any load not specifically permitted by the Code Car ventilation equipment Car receptacles Car heating or air‑conditioning 620.22 9. 137 – 2026 code change part 21A Directly Controlled Luminaire (DCL) provides emergency illumination when: Its control input is disconnected by a listed ELCD It receives an active emergency signal It is listed for emergency use It is supplied by a dedicated emergency branch circuit 700.24 B 10. 61 – 2026 code change part 21When one or more pieces of equipment include an integral load‑management control, the system must be: Marked to indicate that load management is provided Installed only by the utility Limited to single‑phase installations Protected by a separate disconnect 625.42 A 11. 124 – 2026 code change part 21 Fire pump supply conductors may be installed as part of which type of listed cable system? Fire‑resistant cable system High‑temperature cable system Weather‑resistant cable system Emergency‑rated cable system 695.7 A 2 3 12. 40 – 2026 code change part 21The field‑applied marking on an elevator control panel must meet the requirements for: 110.21 B Working space clearances Selective coordination Grounding and bonding continuity 620.16 13. 88 – 2026 code change part 21The vertical bonding zone for perimeter surfaces now extends 3 ft above and 3 ft below the maximum water level 3 ft above only 2 ft above and 2 ft below the water level 5 ft above the deck 680.26 B 2 14. 29 – 2026 code change part 21Which of the following conductors may be installed without GFPE protection when supplying marina or pier equipment? Load‑side conductors of a separately derived system not exceeding 10 feet and installed in a raceway Any feeder less than 50 feet All branch circuits supplying lighting Any conductor supplying monitoring equipment regardless of length 555.35 A 15. 166 – 2026 code change part 21Reconditioned energy storage systems (ESS) are ______ to be installed. Not permitted Permitted Permitted only if listed Permitted only with AHJ approval 706.4 16. 36 – 2026 code change part 21Which of the following is permitted under 590.6(I) for temporary installations? Supporting holiday lighting from vegetation when strain‑relief devices are used Running branch‑circuit flexible cords on the ground if protected by cones Supporting overhead spans of branch circuits from tree branches Using vegetation to support any temporary feeder if GFCI protection is provided 590.6 I Exception 17. 193 – 2026 code change part 21Because Class 2 and Class 3 circuits are power‑limited, alternate requirements are provided for ____ Minimum wire size and overcurrent protection Grounding electrode conductor sizing Raceway bonding and continuity Service disconnecting means 725.1 info note 18. 149 – 2026 code change part 21Legally required standby system switchgear, switchboards, and panelboards shall have an SPD (Surge protection device ) installed integral to or immediately adjacent to ________. The equipment they supply The emergency transfer switch The normal power source The grounding electrode conductor 701.9 19. 132 – 2026 code change part 21If the permanent emergency power source is part of a separately derived system with a grounded conductor, the switching means for the temporary source must: Switch the grounded conductor in accordance with 250.30 Leave the grounded conductor solidly connected Bond the grounded conductor to the building steel Use only non‑metallic raceways 700.4 F 20. 83 – 2026 code change part 21In an indoor pool area, certain equipment may be installed at a minimum height of 7 ft 6 in above the maximum water level if: The branch circuit supplying the equipment is GFCI‑protected The equipment is low voltage The equipment is wet‑location rated The pool is residential 680.22 B 2 21. 199 – 2026 code change part 21Inner system bonding for limited‑energy systems must be connected in accordance with the rules that apply to ____ Grounding and bonding methods in Article 250 Only communications grounding Only Class 1 circuits Only metallic raceways 750.94 22. 79 – 2026 code change part 21A maintenance electrician is replacing a 277‑volt single‑phase lighting circuit that supplies luminaires located directly above an indoor commercial pool. The branch circuit operates at 277 volt to ground and 480 volt phase‑to‑phase. What type of ground‑fault protection is required? Special‑Purpose GFCI Class A GFCI Equipment GFPE set at 30 mA No ground‑fault protection required 680.5 C 23. 118 – 2026 code change part 21Fuel cell system DC circuits shall not exceed __________ volts when installed on or in buildings. 1000 600 750 1500 692.7 24. 46 – 2026 code change part 21Under the 2026 NEC, where must the surge protective device (SPD) be installed for an elevator system? As an integral part of the elevator system or immediately adjacent to the disconnecting means Only at the service equipment supplying the elevator Anywhere within the machine room as long as it is accessible Anywhere within the machine room 620.51 E 25. 135 – 2026 code change part 21Interconnected power production sources that are not designated stored‑energy emergency power sources: Are not required to meet Article 700 requirements Must comply with all Article 700 requirements Must disconnect during emergency operation Must be listed for emergency use 700.12 F 26. 165 – 2026 code change part 21Circulating neutral currents from added power sources can affect ground‑fault protection operation. A common corrective measure is alternative placement of ________. Ground‑fault current sensors Surge arresters Transfer switches Voltage regulators 705.32 & Informational note 27. 174 – 2026 code change part 21A written or ______ record shall be kept of COPS tests and servicing. (This revision modernizing documentation standards by recognizing digital records as equivalent to written records by adopting” record keeping” instead of “written records” the NEC ensures it stays relevant in a digital first operating environments ) Digital Verbal Temporary Archived 708.6 D 28. 131 – 2026 code change part 21A permanent field‑applied label at the emergency system temporary generator connection point must identify: The system voltage The generator fuel type The installer’s license number The building occupancy classification 700.4 F 29. 68 – 2026 code change part 21Cord‑and‑plug‑connected EVSE(electrical vehicle supply equipment )Electric vehicle supply equipment and WPTE(Wireless power transfer equipment ) equipment may use the plug as the disconnecting means when: The rating does not exceed 60 amperes or 150 volts to ground The EVSE is installed in a dwelling unit only The EVSE is used for bidirectional power flow The EVSE is installed outdoors 625.43 A B C 30. 117 – 2026 code change part 21The maximum voltage of a fuel cell system DC circuit is the highest voltage between __________ conductors of a circuit or any conductor and ground. Any two Grounded Parallel Neutral 692.7 31. 105 – 2026 code change part 21Which of the following may serve as a rapid‑shutdown initiating device? A service disconnecting means A lighting switch A thermostat A branch‑circuit breaker 690.12 C 1 32. 146 – 2026 code change part 21 Selective coordination shall be reevaluated if replacement OCPDs supplying emergency loads are not replaced with the same manufacturer and ________. Type Voltage rating Interrupting rating Trip curve 700.32 A B C 33. 69 – 2026 code change part 21Electric vehicle supply equipment and wireless power transfer equipment connected to premises wiring must be installed using: One of the permitted connection methods in 625.44 A through 625.44 C for this type of equipment Any wiring method chosen by the installer Only hard‑wired connections Only flexible cord connections 625.44 34. 159 – 2026 code change part 21Identification of DC power source output conductors shall use color coding, marking tape, tagging, or other approved means in accordance with ________. 705.25(B)(1) through 705.25(B)(3) 705.12(A) 690.31(C)(1) 110.22(A) 705.25 B 35. 19 – 2026 code change part 21Which statement best describes the purpose of the equipotential plane bonding requirements at marinas and similar waterfront facilities? To reduce voltage gradients in areas accessible to personnel To provide a low‑impedance path for lightning strikes only To eliminate the need for GFCI protection on dock receptacles To allow the use of reduced‑size grounding conductor 555.14 36. 64 – 2026 code change part 21Electric vehicle supply equipment and wireless power transfer equipment must be provided with: (The 2026 revision significantly reorganized and expands the requirements for disconnecting means related to electrical vehicle supply equipment and wireless power transfer equipment. the update addresses modern installation conditions previously a disconnect was only required for equipment rate at 60 amps or more and with more than 150 volts to ground however it is now necessary for all EVSE equipment ) One or more disconnecting means as required for the installation A disconnect only when rated over 60 amperes A disconnect only when installed outdoors A disconnect only when serving multiple vehicles 625.43 37. 63 – 2026 code change part 21For electric vehicle charging equipment that is not self‑adjusting, the current adjustment setting must be: Set at the time of installation Left at the factory default Adjusted only by the vehicle owner Changed automatically based on temperature 625.42 B 38. 176 – 2026 code change part 21Table 720.4(A) lists the ______ covered by the general requirements of Article 720. (By explicitly referencing this table 720 .4 A this revision enhances code usability consistency and enforceability for systems that operate at lower power levels section 720.4 A introduces cross reference table that aligns general limited energy system requirements with specific articles governing these various technologies this centralized referencing system is a great addition ) Limited energy installations Overcurrent devices Grounding electrode systems Raceway fill calculations Table 720.4 A 39. 81 – 2026 code change part 21A 240‑volt electric pool water heater has a nameplate load of 44 A. What is the minimum ampacity of the branch‑circuit conductors? 55 A 44 A 50 A 60 A 680.10 A 2 40. 98 – 2026 code change part 21PV system DC circuits on or attached to buildings may not exceed: 1000 volts 600 volts 1500 volts 2000 volts 690.7 41. 164 – 2026 code change part 21Current‑carrying neutral conductors from power sources connected on the load side of ground‑fault protection can cause ________ of the ground‑fault protection due to circulating neutral currents. Oversensitization or desensitization Overvoltage Reverse polarity Excessive impedance 705.32 & Informational note 42. 200 – 2026 code change part 21Inner system bonding requirements apply to both limited‑energy systems and ____ Systems operating at 1000 volts or less Only fire alarm systems Only Class 2 circuits Only communications circuits 750.94 43. 35 – 2026 code change part 21What documentation must be provided to the AHJ after GFPE system testing? A written record of the approved testing method and results A copy of the marina’s insurance policy A list of all receptacles on the pier A statement that the system was energized 555.35 F 44. 99 – 2026 code change part 21The maximum current of a Solar Photovoltaic system ( PV) source circuit may be calculated using which of the following? One of the methods in 690.8(A)(1) or 690.8(A)(2) Only the inverter output rating Only the conductor ampacity Only the short‑circuit current at 25°C 690.8 A 45. 172 – 2026 code change part 21The authority having jurisdiction (AHJ) shall ______ a test of the completed COPS (Critical operations power systems ) system upon installation. Conduct or witness Review Approve Delegate 708.6 A 46. 17 – 2026 code change part 21A marina installs a new pier distribution system operating at 208/120V single‑phase. What documentation may the AHJ accept? Simplified documentation No documentation Only a manufacturer’s cut sheet A verbal description from the installer 555.9 Exception 47. 5 – 2026 code change part 21Which of the following is an example of an ESV under Article 624? Golf cart Passenger automobile Electric motorcycle Neighborhood electric vehicle 100 definitions 48. 7 – 2026 code change part 21Which definition applies to vehicles such as boats, aircraft, and farm equipment when electrically powered? Electric Self‑Propelled Vehicle (ESV) Electric Vehicle (EV) Plug‑In Hybrid Electric Vehicle (PHEV) Electric Mobility Device (EMD) 100 definitions 49. 129 – 2026 code change part 21 The connection point for the temporary alternate source of power for the emergency system must be marked with: Phase rotation and system bonding requirements Maximum load current only The generator manufacturer The installer and date 700.4 F 50. 16 – 2026 code change part 21When required by the authority having jurisdiction, what must be provided for a pier distribution system? Documentation of the engineered electrical design A load calculation only A one‑line diagram prepared by the installer A certificate of compliance from the marina owner 555.9 51. 143 – 2026 code change part 21Emergency system overcurrent protective devices shall be selectively coordinated with all ________ overcurrent protective devices. Supply‑side and load‑side Feeder and branch Normal and optional standby Ground‑fault and arc‑fault 700.32 A B C 52. 156 – 2026 code change part 21Placards for one‑ and two‑family dwellings shall indicate the location of each permanently installed ________ optional standby power source disconnect. On‑site Portable Temporary Interactive 702.7 A 1&2 53. 33 – 2026 code change part 21What is the purpose of the new coordination and performance testing requirement for marina GFPE systems? To ensure the GFPE system operates correctly as installed on site To verify that GFPE devices are factory‑calibrated To allow reduced levels of ground‑fault protection To eliminate the need for GFCI protection 555.35 F 54. 11 – 2026 code change part 21Recreational vehicle site supply equipment must include receptacles that meet which of the following requirements? ( must be installed at each RV site → The configurations in Figure 551.46(C)(1) (TT‑30, 14‑50, 5‑20, etc.) They shall conform to the configurations in Figure 551.46(C)(1) and be listed as weather‑resistant They shall be tamper‑resistant and listed for wet locations only They shall be GFCI‑protected and listed as child‑safe They shall be installed in accordance with 406.26 and be tamper‑resistant 551.71 55. 62 – 2026 code change part 21 Electric vehicle charging equipment with an adjustable current setting is permitted only when: Restricted access to the adjustment is provided by an approved method The adjustment can be made by the vehicle owner The adjustment is made automatically by the utility The adjustment is accessible without tools 625.42 B 56. 190 – 2026 code change part 21Class 1 power‑limited circuits must be protected according to wiring method rules because their classification requires compliance with ____ Chapter 3 physical protection requirements Chapter 8 communications rules Chapter 7 special conditions Chapter 9 tables only 724.1 info note 57. 123 – 2026 code change part 21One permitted method of protecting fire pump supply conductors is encasement in concrete at least: 2 inches thick 1 inch thick 3 inches thick 5 inches thick 695.7 A2 d1 58. 56 – 2026 code change part 21Without the use of load‑management controls, the supply circuit for EV charging equipment must be sized to: The full load served 50% of the equipment rating The minimum conductor size in Chapter 3 The vehicle’s onboard charger rating only 625.42 59. 31 – 2026 code change part 21What type of ground‑fault requirement applies to fire pump circuits serving marina electrical systems? Ground‑fault monitoring with alarm Ground‑fault protection of equipment GFCI protection SPGFCI protection 555.35 B 60. 91 – 2026 code change part 21A storable pool is installed with a permanent deck that encloses part of the pool’s perimeter and provides access to the pool. Under the 2026 NEC, what additional requirement now applies? The installation must comply with 680.26 equipotential bonding No additional requirements Only GFCI protection is required The deck must be treated as a wet location 680.30 B 61. 144 – 2026 code change part 21Selective coordination shall be selected by a licensed professional engineer or other ________ persons engaged primarily in the design, installation, or servicing of electrical systems. Qualified Certified Registered Authorized 700.32 A B C 62. 60 – 2026 code change part 21A power control system used for EV load management may be: Integral to one piece of equipment Installed only as a standalone device Limited to portable equipment only Required to be field‑assembled 625.42 A 63. 162 – 2026 code change part 21A circuit breaker that is not marked line and load shall be considered ________ for backfeeding. Suitable Unsuitable Temporary Limited 705.30 D 64. 161 – 2026 code change part 21Fused disconnects, unless otherwise marked, shall be considered ________ for backfeed. Suitable Unsuitable Conditional Limited 705.30 D 65. 188 – 2026 code change part 21 Although Class 1 circuits are power‑limited, they are not treated as limited‑energy systems because they require ____ The same physical protection as general wiring methods No raceway protection Only low‑voltage cable assemblies Installation only in cable trays 724.1 info note 66. 103 – 2026 code change part 21The purpose of the rapid shutdown requirement for PV systems is Reduce shock hazard for firefighters Improve inverter efficiency Reduce voltage drop during normal operation Reduce arc‑flash hazards for electricians 690.12 67. 150 – 2026 code change part 21The SPD required for legally required standby systems must be installed integral to or immediately adjacent to all legally required standby system ________. Switchgear Disconnects Transformers Controllers 701.9 68. 45 – 2026 code change part 21There’s been a revision selective coordination for elevator systems must be reevaluated under which of the following conditions? (Requirements were added to reevaluate selective coordination whenever over current protection is replaced even if deletions are made to the existing elevator system) Whenever overcurrent protection is replaced or when modifications Only when the elevator controller is replaced Only when the short‑circuit current rating of the service changes Only when required by the authority having jurisdiction 620.62 69. 49 – 2026 code change part 21The requirement in article 625 applies to EV connections used for: Charging Charging only Power export only Bidirectional current flow only 625.4 70. 89 – 2026 code change part 21For non‑conductive pool shells, how many bonding attachment points are required under the 2026 NEC? No minimum number of points is required Four uniformly spaced points Two opposite points One point only 680.26 B 2 71. 125 – 2026 code change part 21Emergency system record keeping requires that written or digital records of tests and maintenance be: Kept and made available to authorized personnel Stored only at the fire department Kept for a minimum of 30 days Submitted to the utility annually 700.4 D 72. 18 – 2026 code change part 21Which of the following pier distribution systems requires full engineered documentation, with no option for simplified documentation? 277/480‑volt three‑phase 120‑volt single‑phase 208‑volt single‑phase 240‑volt single‑phase 555.9 Exception 73. 134 – 2026 code change part 21Interconnection equipment for a microgrid‑connected emergency source must be listed to: Isolate emergency loads from non‑emergency loads and normal supply Control load shedding Synchronize all microgrid sources Provide automatic voltage regulation 700.12 F 74. 55 – 2026 code change part 21The rating of the electrical supply to EV charging equipment may be reduced only when: Load‑limiting controls are used to restrict the overall installation rating The EVSE is installed outdoors The EVSE is Level 1 The utility approves a smaller service 625.42 75. 86 – 2026 code change part 21Under the 2026 NEC, the perimeter bonding zone around a pool now extends how far horizontally from the inside pool wall? 3 ft 5 ft 2ft 4ft 680.26 B 2 76. 57 – 2026 code change part 21 Which statement best reflects the requirement for supplying EV charging equipment? The supply circuit must fully support the load unless controlled load‑limiting is used The supply circuit may be undersized if the EVSE is portable The supply circuit must be oversized by 200% The supply circuit rating is determined by the vehicle manufacturer 625.42 77. 95 – 2026 code change part 21Which condition alone triggers the need for an equipotential plane at a aeration pond ? Equipment is within 10 feet of the body of water Equipment is 20 feet from the water Equipment is indoors Equipment is supplied by a 120‑volt circuit 682.33 78. 106 – 2026 code change part 21A rapid‑shutdown initiating devices must be: Readily accessible Installed in the attic Hidden behind equipment Installed only at the inverter 690.12 C 1 79. 127 – 2026 code change part 21When the emergency system relies on a single alternate source that will be disabled for servicing, the emergency system must include: A permanent switching means for a temporary alternate source A portable generator stored indoors A manual transfer switch only . A second permanently installed generator 700.4 F 80. 38 – 2026 code change part 21What information must be field‑marked on an elevator control panel regarding fault current? The available fault current at the panel’s line terminals The building service size The elevator motor full‑load amperes The utility transformer impedance 620.16 81. 65 – 2026 code change part 21In a multifamily dwelling where multiple Electric vehicle supply equipment or wireless power transfer equipment units each have individual disconnects, each unit must have: A plaque or directory identifying which disconnect serves which unit A separate service A disconnect located inside the dwelling unit A lockable meter enclosure 625.43 A B C 82. 177 – 2026 code change part 21Limited energy system grounding is covered in Article ______. 750 725 830 760 Table 720.4 A 83. 66 – 2026 code change part 21When the disconnecting means for permanently connected EVSE and WPTE equipment is installed remote from the equipment, the equipment must have: A plaque or directory indicating the disconnect location A second disconnect A lockable cover A separate grounding electrode 625.43 A B C 84. 198 – 2026 code change part 21Selecting a grounding location that provides the shortest practical bonding conductor or grounding electrode conductor helps reduce ____ Potential differences between limited‑energy circuits and other metal systems The need for additional raceway supports Voltage drop on the limited‑energy circuit Conductor insulation requirements 750.48 info note 85. 185 – 2026 code change part 21Raceways used for limited‑energy systems must be supported and secured according to ____ The general support rules for that raceway type The building owner’s specifications The conductor manufacturer’s instructions instalers descrtion 723.22 A 2 86. 107 – 2026 code change part 21 A photovoltaic system (PV system) disconnecting means must be installed so that it: Simultaneously disconnects PV system conductors not solidly grounded from all other wiring systems Disconnects only grounded conductors Disconnects only ungrounded conductors Disconnects only conductors over 50 volts 690.13 87. 178 – 2026 code change part 21Article 721 covers ______ requirements for limited energy systems. (Power sources for limited energy systems establishes the power source requirements for limited energy system circuits it ensures that power sources are properly selected and protected to maintain reliability and safety they also have to align with the specific characteristics at operational limits of low energy systems ) Power source Grounding Overcurrent protection Wiring 721.1 88. 32 – 2026 code change part 21Which of the following must be true of the fire pump ground‑fault alarm? It must be audible and visual and monitored by qualified personnel It must be visual only It must automatically shut down the fire pump It must be located outdoors near the pier 555.35 B 89. 171 – 2026 code change part 21Commissioning of ESS( Energy storage systems) is required upon installation except in ______. One‑ and two‑family dwelling units Industrial facilities Healthcare facilities Educational occupancies 706.7 B 90. 42 – 2026 code change part 21 What is now required for supplying lighting in each elevator car? (A long standing ambiguous requirement regarding how car lighting in elevators must be wired specifically the update language mandate separate branch circuit for the car lights In each individual elevator car the revised language now clearly requires one branch circuit per elevator car for the car lighting system) One dedicated branch circuit must supply the lighting for each individual car A single branch circuit may supply lighting for multiple cars Lighting must be supplied from the building’s general lighting panel Lighting must be supplied from the elevator machine‑room receptacle circuit 620.22 91. 70 – 2026 code change part 21Cord‑and‑plug‑connected Wireless power transfer equipment and electric vehicle supply equipment when used must be provided with an attachment plug rated at least: 125% of the maximum rating of the equipment 80% of the equipment rating 100% of the equipment rating 150% of the branch‑circuit rating 625.44 92. 147 – 2026 code change part 21Selective coordination shall be reevaluated if replacement OCPDs are not replaced with the same manufacturer and type and with the same ________ or setting. Rating Voltage Frequency Polarity 700.32 A B C 93. 22 – 2026 code change part 21Which statement best reflects the intent of the updated equipotential bonding requirements for marinas? To create consistent bonding standards across all NEC articles involving water‑contact areas To match bonding practices used in dry To allow installers to design their own bonding methods To reduce the number of required grounding electrodes 555.14 94. 100 – 2026 code change part 21The maximum current of a PV source circuit is: The sum of the highest short‑circuit current ratings of modules in parallel × 125% The average operating current The open‑circuit voltage divided by resistance The inverter nameplate current 690.8 A 1 a 1 95. 27 – 2026 code change part 21What is the primary purpose of adding “piers” to the marina ground‑fault protection language? To ensure consistent application of shock‑protection rules across all marinas and extensions of marinas To reduce the number of required GFCI devices To allow installers to choose between two code articles To permit higher voltage systems on floating structures 555.35 96. 47 – 2026 code change part 21The scope of Article 624 covers power transfer systems capable of which type(s) of current flow? Import Import only Export only Alternating current only 624.1 97. 140 – 2026 code change part 21Devices that combine control signals with Class 4 emergency power on a single circuit must be: Listed as ELCDs Capable of isolating normal power sources Listed as emergency luminaires nstalled in separate raceways 700.28 A 98. 153 – 2026 code change part 21If a shutdown occurs due to an overloaded condition, reconnection of the supply shall only be performed ________. Non‑automatically Automatically Remotely By the PCS controller 702.4 A 3 Informational note #1 and #2 99. 154 – 2026 code change part 21PCS functionality is typically used to control loads at the ________, feeder, distribution level, or a combination of both. Branch‑circuit Service disconnect Transfer switch Metering point 702.4 A 3 Informational note #1 and #2 100. 52 – 2026 code change part 21The SCCR of EVSE may be established using: A listed and labeled assembly or an approved method The vehicle’s onboard charger rating Any method chosen by the installer The utility’s transformer impedance 625.5 2 Back Save Progress Retry Finish