  1. 1. 149 – 2026 Changes Part 1

    1

    Which of the following correctly describes the requirements for grounding switches used in medium‑ and high‑voltage equipment?(This new section brings clarity and structure to the application by mandating key safeguards that help prevent accidental energization or unsafe switching sequences )

    Reference:495.26
  2. 2. 172 – 2026 Changes Part 1

    1
    Part II of Article 517 does NOT apply to which of the following spaces?
    Reference:517.10 B
  3. 3. 138 – 2026 Changes Part 1

    1

    According to 2026 NEC when a generator set is equipped with a listed overcurrent protective device or a combination of a current transformer and overcurrent relay, conductors are permitted to be tapped from the load side of the protected terminals under which condition?

    Reference:445.13 B
  4. 4. 7 – 2026 Changes Part 1

    1
    As a general rule, in dwelling units, outdoor circuits rated at 150 volts or less to ground require GFCI protection for __________. (This increase addresses the trend for larger HVAC units now being installed in residential applications.)
    Reference:210.8 F
  5. 5. 12 – 2026 Changes Part 1

    1
    ___________ that include cooking facilities which have permanent provisions for cooking shall now meet the kitchen small applicance branch circuit AFCI and GFCI requirements of dwelling units. (Previously only guest rooms and suites in hotels or motels were required.)
    Reference:210.17
  6. 6. 62 – 2026 Changes Part 1

    1
    The scope of new NEC Article 267 covers _______ operating at 1000 volts AC or 1500 volts DC. (Previously located in Article 235 along with other higher voltage systems.)
    Reference:267.1
  7. 7. 155 – 2026 Changes Part 1

    1
    Which of the following bonding methods is not permitted for normally non–current?carrying metal parts in hazardous classified locations?(Vision grounding and bonding requirements for hazardous locations were found in three different locations )
    Reference:500.30 B
  8. 8. 92 – 2026 Changes Part 1

    1
    Nonmetallic-Sheathed Cable (Type NM and NMC, Romex) shall not officially be used _________. (Prior editions of the NEC did not specifically prohibit this.)
    Reference:334.12
  9. 9. 35 – 2026 Changes Part 1

    1
    In ___________ installations with multiple energy sources, those sources not located adjacent to the service disconnect must now be marked and identified on the plaque or directory with their location. (Many of these more common disconnects are installed in locations such as garages, sheds, basements, and rooftops.)
    Reference:230.70 D
  10. 10. 73 – 2026 Changes Part 1

    1
    When raceways are installed in a wet location above grade level they now shall _______. (Moisture accumulation can be an issue in environments such as food processing plants, car washes, and swimming pools.)
    Reference:300.11 B
  11. 11. 52 – 2026 Changes Part 1

    1
    A grounding electrode conductor ________ through ventilation, mounting slots, or weep holes of an enclosure like a transformer. (To address a common misapplication in the field risking mechanical damage to the GEC, affecting water drainage, and GEC support.)
    Reference:250.64 G
  12. 12. 22 – 2026 Changes Part 1

    1
    When a laundry area is located inside a closet or compact enclosure, both the lighting outlet and the control device _________. (To reflect common small laundry rooms such as in multifamily applications.)
    Reference:210.70 A ex 3
  13. 13. 71 – 2026 Changes Part 1

    1
    Wording was changed to clarify that ________ direct buried conductors and raceways buried at least 18 inches shall have their location identified by a warning label. (It was a common misconception that this rule only applied to directly buried conductors and not also buried raceways.)
    Reference:300.7 D3
  14. 14. 45 – 2026 Changes Part 1

    1
    When installing a Type 2 Surge Protection Device (SPD), the NEC provides 3 situations with separate subpart requirements. The installer shall ___________. (The previous interpretation was considered impractical and sometimes technically incompatible.)
    Reference:242.14
  15. 15. 78 – 2026 Changes Part 1

    1
    In the ampacity tables, the temperature rating of conductor type XHWN has been changed and it now sits in the _________ column of the table. (An example of a correction because XHWN was in the wrong column in previous code cycles.)
    Reference:310.16
  16. 16. 140 – 2026 Changes Part 1

    1
    A key 2026 NEC update revises transformer overcurrent protection requirements to improve clarity and usability. Which of the following best reflects the nature of this revision?
    Reference:450.3
  17. 17. 97 – 2026 Changes Part 1

    1
    A new mandate requires that when a raceway such as IMC with threads enters an enclosure, a locknut or fitting ______ be installed on the inside and outside of the enclosure. (This rule was buried in the bonding and grounding section so was sometimes not installed as required.)
    Reference:342.29
  18. 18. 186 – 2026 Changes Part 1

    1
    Article 525 of the 2026 NEC covers the installation of portable wiring and equipment for which of the following?( Revised article 525 clarify the requirements for temporary power systems in entertainment settings these changes are not only editorial but structural making the article easier to navigate implement and enforce in high risk venues ware public safety is essential)
    Reference:525.1
  19. 19. 2 – 2026 Changes Part 1

    1
    New Article 206 outlines the general requirements for ________. (Non-Powered-Limited circuits can pose a bigger risk for fire and shock. Previously this content was limited to Chapter 3.)
    Reference:206.1
  20. 20. 120 – 2026 Changes Part 1

    1
    As a general rule (disregarding exceptions), only which of the following conductors are permitted to be located within a switchboard or switchgear section?
    Reference:408.10 2
  21. 21. 96 – 2026 Changes Part 1

    1
    For Intermediate Metal Conduit (IMC) __________ now permitted as an acceptable means to prevent galvanic corrosion when joining dissimilar metals. (This comes up in retrofits such as industrial expansions or changes.)
    Reference:342.14
  22. 22. 193 – 2026 Changes Part 1

    1
    Which of the following equipment used in motion picture and television studios and remote locations is REQUIRED to be listed under Article 530?(These listing requirements ensure that all portable power and lighting equipment used in production environments meets tested safety standards, especially where temporary wiring, high?intensity lighting, and rapid setup/teardown create elevated hazards.)
    Reference:530.2
  23. 23. 98 – 2026 Changes Part 1

    1
    A revised section for cable trays now requires a minimum space of ________ above the cable tray for access unless an exception is met. (In many commercial, industrial, and data centers these trays can become very congested.)
    Reference:392.18 F
  24. 24. 169 – 2026 Changes Part 1

    1
    Additional sources of electrical service permitted to supplement the utility service in healthcare facilities shall have the capacity and rating to meet the maximum actual demand likely to be produced by the connected load. Demand calculations for sizing these systems shall be based on one or more of the following EXCEPT __________.
    Reference:517.4 B
  25. 25. 175 – 2026 Changes Part 1

    1

    According to the 2026 NEC, the requirements of Article 700 shall NOT apply to which of the following?(This change addresses the impracticality of applying article 700 to all components of the electrical essentials system the change emphasizes only life safety branch of the essential electrical system must comply with 700 )

    Reference:517.26
  26. 26. 131 – 2026 Changes Part 1

    1
    Reconditioned motors are permitted to be installed only if the reconditioning has been performed in accordance with which of the following?
    Reference:430.3
  27. 27. 151 – 2026 Changes Part 1

    1
    What was the purpose of adding Parts VI and VII to Article 495 in the 2026 NEC?(The 2026 NEC introduces two entirely new parts article 495 parts VI and VII , expanding coverage beyond just transformers to include other types of oil insulated medium and high voltage equipment )
    Reference:article495 parts VI andVII
  28. 28. 55 – 2026 Changes Part 1

    1
    A new NEC section now covers the method required to establish an effective ground fault path when installing a nonmetallic enclosure with metallic raceways. Generally, ________ metallic wiring method shall have bonding jumpers or fitting. (Although uncommon, there are specially designed and listed nonmetallic enclosures with built in metal bonding.)
    Reference:250.109 B2
  29. 29. 50 – 2026 Changes Part 1

    1
    A building service with multiple disconnecting means in separate enclosures is allowed to use a common grounding electrode, with a tap to each disconnect __________. (The format also changed from a dense paragraph to the list-style because of common misapplications and inconsistent interpretations.)
    Reference:250.64 D1
  30. 30. 33 – 2026 Changes Part 1

    1
    Service disconnects in other than one- and two-family dwellings shall now be marked _______. (To also help reduce delays and confusion for first responders and utilities, especially with services with multiple disconnects such as solar.)
    Reference:230.70 B
  31. 31. 156 – 2026 Changes Part 1

    1

    Which of the following statements correctly reflects the revised requirements for reconditioned equipment used in hazardous (classified) locations?

    Reference:501.3
  32. 32. 158 – 2026 Changes Part 1

    1
    In Class I, Division 1 locations, one or more of the wiring methods in__________ shall be used in accordance with the requirements of the sections in the reference column and with the respective wiring?method requirements applied. For example, Type P cable is permitted only in __________ industrial establishments.(This update puts the code into table form for improve usability enabling installers to more clearly determine which wiring methods are allowed )
    Reference:501.1
  33. 33. 161 – 2026 Changes Part 1

    1
    According to the NEC, an electric vehicle connector shall NOT be located within a __________ location as defined in 511.5.
    Reference:511.10 B 2
  34. 34. 187 – 2026 Changes Part 1

    1
    Where multiple services or separately derived systems supply a portable structure and the sources are separated by less than 3.7 m (12 ft), which of the following is REQUIRED?(Generators are commonly used in these types of areas due to limited or inaccessible permelectrical infrastructure and this new language establishes clear consolidated requirements for grounding and protection that was previously all over other sections in the National Electric Code )
    Reference:525.12
  35. 35. 77 – 2026 Changes Part 1

    1
    The text in the NEC relating to when the neutral conductor should be counted as a current-carrying conductor for ampacity adjustment in raceways has been reorganized and also written into a list format. A neutral conductor that only carries the unbalanced current (linear load) from the other conductors in the same circuit is _______. (The current ratings of conductors has been evolving and changing in the NEC since the late 1800s.)
    Reference:310.15 E
  36. 36. 110 – 2026 Changes Part 1

    1
    In the 2026 NEC, wiring?device–type switch requirements were relocated from Article 404 to which Article?
    Reference:406
  37. 37. 53 – 2026 Changes Part 1

    1
    The NEC requirement to provide an Intersystem Bonding Termination (IBT) device at the service equipment and separate structure now additionally able to be secured and connect directly to ___________. (ITBs are used as a common grounding point for other systems like telephone, cable, and broadband. These are frequently grounded improperly if at all.)
    Reference:250.94 A
  38. 38. 141 – 2026 Changes Part 1

    1
    According to 2026 NEC why are reconditioned capacitors not permitted to be installed?(The 2026 NEC introduces a new provision ,reconditioning which makes a Definitive and safety driven statement” reconditioned capacitors must not be installed”)
    Reference:460.3
  39. 39. 44 – 2026 Changes Part 1

    1
    Surge protective devices (SPDs) and surge arresters used for critical overvoltage protection ________. (This change brings SPD in line with other NEC code sections.)
    Reference:242.3
  40. 40. 148 – 2026 Changes Part 1

    1

    According to 2026 which of the following correctly describes the requirements for isolating means used to completely isolate equipment from all ungrounded conductors (other than service conductors)?

    Reference:495.22
  41. 41. 135 – 2026 Changes Part 1

    1

    According to 2026 NEC the outdoor disconnecting means for a split‑system HVAC unit in other than one‑ and two‑family dwellings must be marked with which of the following?

    Reference:440.15
  42. 42. 57 – 2026 Changes Part 1

    1
    New Article 265 now specifically covers branch circuits over 1000 volts AC and 1500 volts DC but also additionally recommends _________ for additional information. (Content relocation from Article 235 to restructure low-voltage (LV) and medium voltage (MV) systems.)
    Reference:265.1
  43. 43. 145 – 2026 Changes Part 1

    1

    According to 2026 NEC what provision must be included in stationary battery installations to prevent damage and hazards?( this updates battery safety requirement , to control Thermal runaway especially in lithium-ion chemistry , gas buildup inventing in lead acid and nickel cadium systems , swelling, fire, or explosions and to keep battery life at its maximum )

    Reference:480.14
  44. 44. 64 – 2026 Changes Part 1

    1
    For services over 1000 volts AC or 1500 volts DC, if the short circuit protection device (OCPD) is not an integral part of the service disconnecting means, it ________ (to assure that the disconnect is readily accessible.)
    Reference:268.91 B
  45. 45. 115 – 2026 Changes Part 1

    1

    Receptacles shall not be installed in a face‑up position in which of the following locations? (The NEC prohibits installing receptacles face‑up on work surfaces because liquids can spill directly into the device,debris can fall into the openings and It creates a shock and contamination hazard)

    Reference:406.14 G
  46. 46. 136 – 2026 Changes Part 1

    1
    According to 2026 NEC when overcurrent protection is not provided at the generator terminals, the ampacity of the conductors from the generator terminals to the first distribution device containing overcurrent protection shall be not less than which of the following?
    Reference:445.13
  47. 47. 80 – 2026 Changes Part 1

    1
    Information on electrical equipment that is required to be listed scattered throughout Chapter 3 has been relocated into one new section and now includes ________. (The term listed means a product that has been tested and certified by a Nationally Recognized Testing Laboratory (NRTL) such as UL or ETL.)
    Reference:314.2
  48. 48. 198 – 2026 Changes Part 1

    1
    Outdoor receptacle outlets installed on mobile or manufactured homes must now comply with which NEC section?(Again this section is now in alignment with the requirements for stick built homes )
    Reference:550.13 D
  49. 49. 48 – 2026 Changes Part 1

    1
    The NEC section regarding ground rod and pipe electrodes has been revised. Burying the electrode in a trench 30 inches deep ___________. (Arguably the most common use in residential and commercial applications, this revision should clarify the previous intent.)
    Reference:250.53 A4
  50. 50. 41 – 2026 Changes Part 1

    1
    A new section in NEC article 240 identifies what overcurrent protective devices (OCPDs) are suitable and approved for providing branch-circuit, feeder service conductors and electrical equipment including _________. (The intent was to create one location for users that identified the types of breakers and fuses that the NEC recognized.)
    Reference:240.7
  51. 51. 72 – 2026 Changes Part 1

    1
    A new option item ________ was added to address areas where raceways were subject to temperature changes that can cause condensation. (The circulation of warm area such as into a cold storage is the primary cause of condensation in raceways that can then drip into electrical enclosures.)
    Reference:300.9 A
  52. 52. 16 – 2026 Changes Part 1

    1
    There is now a new size limitation to permit a ______ minimum size Copper-Clad Aluminum Conductor to serve lighting outlets and exhaust fans in bathrooms and laundry rooms. (A Copper-Clad conductor has copper on the outside and aluminum in the center. Be sure to use wirenuts rated for copper and aluminum AL/CU.)
    Reference:Table 210.24(2)
  53. 53. 200 – 2026 Changes Part 1

    1
    Service equipment is permitted to be installed in or on a manufactured home only if which condition is met?
    Reference:550.51 B 1-7
  54. 54. 176 – 2026 Changes Part 1

    1
    A sign must be placed at the service?entrance equipment indicating the type and location of each on?site power source. Which of the following is exempt from this signage requirement?
    Reference:517.28 A ex.
  55. 55. 180 – 2026 Changes Part 1

    1
    An EES that uses a single on?site power source must include a permanent switching means to connect a portable or temporary on?site power source. Which of the following is REQUIRED?(Temporary power source connection refers to an intern power source used in the primary power source is unavailable or during maintenance )
    Reference:517.30 E 4
  56. 56. 197 – 2026 Changes Part 1

    1

    Which of the following best describes the updated GFCI requirement for receptacle outlets in Article 550?(Instead of specifying certain appliances and locations in a mobile or manufactured home the language Changed to reference section 210.8 This completely removes any differences between the old mobile home requirements And stick built home requirements )

    Reference:550.13 B
  57. 57. 63 – 2026 Changes Part 1

    1
    New NEC Article 268 covers services over 1000 volts AC or 1500 volts DC and acknowledges that supervised installations can have grounding and bonding designed by _______. (A formal introduction of customized conductor sizing for high voltage systems.)
    Reference:268.42 C
  58. 58. 27 – 2026 Changes Part 1

    1
    Outside feeders to one- and two-family dwelling units required a disconnect and an emergency disconnect, a clarification states ______. (Meant to reduce added costs and complexity with simple structures like residential workshops and detached garages.)
    Reference:225.31 A, 4 1
  59. 59. 26 – 2026 Changes Part 1

    1
    NEC Article 225 covering outside branch circuits or feeders _______ the requirements in Article 210 covering inside branch circuits and Article 215 which convers inside feeders. (This clarification should help installers not to assume that only Article 225 applies to installations.)
    Reference:225.1 Note 2
  60. 60. 114 – 2026 Changes Part 1

    1

    On work surfaces, receptacles shall not be installed in a face‑up position unless which condition is met?

    Reference:406.14 G
  61. 61. 67 – 2026 Changes Part 1

    1
    A new NEC section identifies conductors that are considered damaged and now would require replacement including _________. (This damage can compromise insulation ratings and cause short circuits.)
    Reference:300.4 C
  62. 62. 13 – 2026 Changes Part 1

    1
    A new exception now states that _________ individual branch circuits are not allowed to supply receptacle loads. (Because of the standard plug and receptacle ratings there would be a potential for overloading.)
    Reference:210.22 ex
  63. 63. 125 – 2026 Changes Part 1

    1

    The NEC requires central heating equipment to be supplied by an individual branch circuit. Under the 2026 revision, which additional load is permitted on the same branch circuit?

    Reference:422.12
  64. 64. 116 – 2026 Changes Part 1

    1
    Which of the following is required for a faceplate that incorporates a night light and is installed over a receptacle outlet?
    Reference:406.16 D
  65. 65. 14 – 2026 Changes Part 1

    1
    In a major change, there is now a new size limitation to permit a ________ minimum size copper conductor to serve lighting outlets and exhaust fans in bathrooms and laundry rooms. (Current demand can now be relatively lower in homes with LED lighting and compact fan units are standard)
    Reference:210.24(1)
  66. 66. 181 – 2026 Changes Part 1

    1

    When an EES uses more than one on-site power source, which of the following is REQUIRED when any single on-site source is disabled for service?

    Reference:517.30 F 1
  67. 67. 11 – 2026 Changes Part 1

    1
    Branch-circuit disconnecting means rated 1000 amperes or more, solidly grounded, but not exceeding ____ volts line to line now mandates GFCI protection even for DC systems. (The NEC is trying to keep up with the increased usage of DC power such as in data centers, EV charging, energy storage systems, and large scale solar.)
    Reference:210.13 A&B
  68. 68. 65 – 2026 Changes Part 1

    1
    The NEC created Article 270 to cover grounding and bonding for systems over 1000 volts AC or 1500 volts DC. Grounding for systems _________ is now also covered. (These systems can be specialized with increased risk of ground touch potential.)
    Reference:270.20 C
  69. 69. 130 – 2026 Changes Part 1

    1

    A key update in Article 430 of the 2026 NEC consists of officially recognizing which motor designs throughout the article? (These motors are very efficient and introduce new ways to calculate lock rotor current and properly sized circuit parts )

    Reference:Recognition throughout article 430
  70. 70. 93 – 2026 Changes Part 1

    1
    There was a change for Service Entrance Cables (SE and USE) to allow relief for flat cables when bent on the flat side of the cable. _______________. (these flat versions are very common in residential applications.)
    Reference:338.24
  71. 71. 34 – 2026 Changes Part 1

    1
    There are now enhanced marking requirements for one- and two-family residential service disconnects and specifically state that the marking ______. (Some state rules also have additional requirements.)
    Reference:230.70 B2
  72. 72. 61 – 2026 Changes Part 1

    1
    New Article 266 covers feeders over 1000 volts AC or 1500 volts DC. The concept of “supervised installations” was added and permits a reduction in standard conductor sizing. The work of a supervised installation must be performed by ________. (The NEC is working to accommodate these unique high voltage systems.)
    Reference:266.4 C
  73. 73. 167 – 2026 Changes Part 1

    1

    Each dispensing device shall be provided with a means to remove all external voltage sources during maintenance and service. This disconnecting means shall remove ungrounded and grounded power conductors, communication, data, and video circuits. The location of this means is permitted to be __________.

    Reference:514.13
  74. 74. 88 – 2026 Changes Part 1

    1
    For Mineral-Insulated, Metal-Sheathed Cable (Type MI) the _________ is not required to be listed and identified. (There is an increasing demand for these systems’ reliability and safety.)
    Reference:332.2
  75. 75. 179 – 2026 Changes Part 1

    1
    Power sources for the Essential Electrical System (EES) shall be one or more of the following: (These updates ensure that both on site and off site power sources are designed for sufficient reliability to support the faculties emergency operation plan )
    Reference:517.30 B
  76. 76. 94 – 2026 Changes Part 1

    1
    An update to Underground Feeder and Branch-Circuit Cable (Type UF) now permits the use of _______ conductors as the minimum size for this burial type cable. (This popular cable commonly used in residential and light commercial underground applications can run long distances so this change can be a considerable cost savings.)
    Reference:340.104
  77. 77. 99 – 2026 Changes Part 1

    1
    Updated language for cable trays now allows ________ rated 2000 volts or less in the trays. (The terminology “evenly distributed across the cable tray” was eliminated, replacing it with conductor count and size. That term was used to encourage proper heat dissipation but it was hard to enforce.)
    Reference:392.22 B
  78. 78. 36 – 2026 Changes Part 1

    1
    The NEC clarified that a remote control device a service disconnect ____ as the service disconnect itself is meeting those requirements (such as push buttons, relay circuits, or wireless controllers.)
    Reference:230.70 F
  79. 79. 8 – 2026 Changes Part 1

    1
    For a dwelling unit outdoor outlet replacement for listed HVAC equipment, _____________. (This should help this industry with unwanted tripping because standard GFCIs were incompatible.)
    Reference:210.8 F ex 3
  80. 80. 100 – 2026 Changes Part 1

    1
    Terminology for Low-Voltage Suspended Ceiling Power Distribution Systems was replaced, now requiring that all components shall be _________. (Careful installation is needed to avoid damage or fire risks for these increasingly common systems.)
    Reference:393.14 A
  81. 81. 25 – 2026 Changes Part 1

    1
    Surge-Protection Devices (SPDs) on feeders has been expanded beyond residential occupancies to now include __________. (To safeguard electronic equipment in sleeping and living quarters such as smoke alarms.)
    Reference:215.18 A
  82. 82. 196 – 2026 Changes Part 1

    1
    The construction of an equipotential plane shall comply with which NEC subsections?(This change introduces new detailed construction requirements for a quick potential planes in agricultural buildings )
    Reference:547.44 C
  83. 83. 3 – 2026 Changes Part 1

    1
    Ground-Fault Circuit-Interrupter Protection (GFCI) requirements in dwelling units have made adjustments to include storage and work areas not intended as habitable rooms ______________. This modification is intended to decrease hazards.
    Reference:210.8 A
  84. 84. 184 – 2026 Changes Part 1

    1
    Overcurrent protective devices serving the Essential Electrical System (EES) must be coordinated for the period of time that a fault’s duration extends beyond which of the following?(The addition of subsection F is a critical enhancement to the National Electric Code in 2026 as it addresses the need for precise coordination of over current protective devices in EES ‘s. This author thinks precise coordination is needed in all applications, who wants a main fuse blowing or circuit breaker turning off everything that you are addressing in whichever system you’re addressing? Life safety of course is more urgent )
    Reference:517.42 F
  85. 85. 144 – 2026 Changes Part 1

    1
    According to 2026 NEC which of the following must be grounded in stationary battery installations?(This update clarifies outdated text by adding clear requirements That are very actionable :All conductive battery rack stands cabinets and cases must be grounded)
    Reference:480.8
  86. 86. 119 – 2026 Changes Part 1

    1
    According to the NEC, which of the following types of equipment is not permitted to be reconditioned?
    Reference:408,3 B
  87. 87. 18 – 2026 Changes Part 1

    1
    A change in determining the required receptacle outlet placement in dwelling units was a revision to exclude _________ from the wall space measurements. (The purpose was to reduce the overuse of extension cords. This should simplify the task of laying out receptacle outlet locations in the home.)
    Reference:210.52 A2(1)
  88. 88. 70 – 2026 Changes Part 1

    1
    The requirement to maintain a 1 1/2 inch spacing from a roof decking for cables, raceways, and boxes now includes a decking poured with light weight concrete at least ______. (It is common during roofing repairs or replacement to use long screws that can penetrate wiring methods.)
    Reference:300.6 E
  89. 89. 49 – 2026 Changes Part 1

    1
    Grounding electrode conductors shall generally be continuous without a splice. A new exception to that rule includes ______ that is accessible. (Please note that this new option must be accessible for inspection and maintenance after installation…does that include burial?)
    Reference:250.64 C
  90. 90. 1 – 2026 Changes Part 1

    1
    A new list item now permits grounded neutral conductors sized 6 AWG and smaller with white or gray insulation to have a ________. (This should help match a neutral to the corresponding phase conductors in a raceway with other conductors. ( This has already been done in other countries.)
    Reference:200.7 A
  91. 91. 162 – 2026 Changes Part 1

    1
    Cannabis extraction operations shall NOT be located in any building containing which of the following occupancies?
    Reference:512.6
  92. 92. 113 – 2026 Changes Part 1

    1
    Non grounding type receptacles with no grounding conductor present can be replaced with_______.
    Reference:406.12 D 1
  93. 93. 105 – 2026 Changes Part 1

    1
    Article 404 requires switches to be installed in easily accessible locations. What is the maximum permitted height to the center of the grip of the operating handle when the switch is in its highest position?
    Reference:404.10 A 2
  94. 94. 163 – 2026 Changes Part 1

    1

    Where cannabis oil booths are provided with a gas detection system installed in accordance with 500.7(K) or 505.8(I), electrical equipment listed for __________ shall be permitted.

    Reference:512.21
  95. 95. 199 – 2026 Changes Part 1

    1
    Which of the following is TRUE regarding service equipment for a mobile home under Article 550?
    Reference:550.51
  96. 96. 104 – 2026 Changes Part 1

    1

    When using reconditioned switches, not all types are permitted to be installed. Which one is not permitted under the 2026 National Electrical Code?(General‑use snap switches fall under the category of wiring devices, and the NEC explicitly prohibits reconditioning of wiring devices )

    Reference:404.3 B
  97. 97. 109 – 2026 Changes Part 1

    1

    According to the NEC, which of the following statements about reconditioned wiring devices is correct?(Wiring devices cannot be reconditioned because they’re inexpensive are safety critical have internal components that cannot be inspected and are not designed for refurbishment )

    Reference:406.3
  98. 98. 121 – 2026 Changes Part 1

    1
    A new NEC revision adds requirements for identification and labeling of switchboards, switchgear, and panelboards. Under this revision, which section must these assemblies comply with?
    Reference:408.10 F
  99. 99. 139 – 2026 Changes Part 1

    1
    According to the 2026 NEC the terminology for generator remote emergency shutdown has been modernized by replacing an old term emergency stop switch with_______. (This update reflects the evolution of generator control technologies which increasingly rely on digital systems programmable interfaces and network control circuits rather than physical traditional switches )
    Reference:445.19 B
  100. 100. 150 – 2026 Changes Part 1

    1

    According to 2026 NEC which of the following requirements applies when switchgear is installed over a combustible floor?

    Reference:495.36